10th Street Project
Des Moines, Iowa
In 2007 Northwest Steel Erection erected a particularly unique structure in downtown Des Moines. This structure was a mixed
use building consisting of a 9-story precast parking ramp and a 5-story office on top. Northwest Steel erected over 1800 pieces
of structural precast with a Manitowoc 2250 crane. The structural precast was fabricated by IPC of Des Moines. The structural
steel was fabricated by Drake Williams Steel. Ball Construction was the general contractor for the entire project.